Project Time Budget |
|||
| Budget Items | Projected Hours | Actual Hours | Difference |
| Planning | |||
| Mission Statement | 1.0 | 1.5 | -0.5 |
| User Definition | 1.0 | 2.0 | -1.0 |
| Content Selection | 2.0 | 2.0 | 0 |
| Mockup 1 | 1.0 | 2.5 | -1.5 |
| Subtotal Task Hours | 5.0 | 8.0 | 3.0 |
| Analysis | |||
| User Feedback | 2.0 | 3.0 | -1.0 |
| Modifications to Mockup 1 | 1.0 | 0.5 | -0.5 |
| Mockup 2 | 2.0 | 1.0 | -1.0 |
| Write Up | 2.0 | 3.0 | -1.0 |
| Subtotal Task Hours | 8 | 7.5 | 3.5 |
| Design | |||
| Final Mockup | 4 | ||
| Webpage Layout | 15 | ||
| Home Page Design | 15 | ||
| Subtotal Task Hours | 34 | ||
| Implementation | |||
| Content Acquisition | 6 | ||
| Content Editing | 11 | ||
| Page Implementation | 6 | ||
| Design Revisions | 15 | ||
| Testing | 10 | ||
| Subtotal Task Hours | 48 | ||
| Operation/Maintenance N/A | |||
| Evaluation N/A | |||
| Total Task Hours | 95 | ||